CB6 to vote on sanitation garage alternatives

Site for the proposed sanitation garage (Photo by Maria Rocha-Buschel)

Site for the proposed sanitation garage (Photo by Maria Rocha-Buschel)

By Maria Rocha-Buschel

Community Board 6 will soon be reviewing alternative proposals for the planned sanitation garage at the Brookdale campus from the board’s Land Use and Waterfront Committee. The proposals, which had been put together by a firm hired by CB6, BFJ Planning were presented to the committee last Wednesday and the full board will be voting on them soon.

The presentation at the most recent Land Use and Waterfront Committee meeting didn’t offer any major changes in the proposals that committee members had already heard from BFJ, but the plan was more complete than in previous meetings.

“(The proposals) are more detailed and accurate now because they’re based on feedback from the committee and site visits that we’ve done,” CB6 chair Sandro Sherrod said. “Both plans have positive benefits and both have their downsides but there’s a lot of interest about this in the community and there’s still more work that needs to be done to flesh out either plan.”

The first alternative that BFJ Planning presented includes the construction of a garage on the proposed Brookdale site at East 25th Street and First Avenue, but in a different configuration from that of DSNY’s proposal. BFJ’s plan would include a partially-underground garage at the Brookdale site that would allow for other uses above ground such as affordable housing, senior housing or health-related facilities. The proposal allows for a building with less height and longer ramps so that the garage can accommodate the same number of vehicles without being as imposing.

The second alternative would place the garage at the Con Edison facility at Avenue C near East 14th Street.

Although this plan would involve construction at Murphy’s Brother’s Park, the plan would actually move the open space rather than get rid of it; one of the purported benefits of this alternative proposal is that it would ultimately add 1.7 acres to the park once the project was completed.

Sherrod said that the full board was scheduled to meet this past Wednesday and it was possible the garage might not be discussed then, although the meeting is after T&V’s press time for this week. If the vote on the garage proposals did not occur on Wednesday, Sherrod said they would be discussed at next month’s full board meeting.