The contractors working at the hospital site faced delays due to difficulties drilling through found materials like concrete and rocks and a tentative projected finish date for the project is the end of the year, with work on the Asser Levy Park side expected to be finished some time this summer. (Photo by Anne Greenberg)
By Sabina Mollot
Last August, Town & Village reported on how the project to build a flood wall outside the VA Medical Center was scheduled to be finished by March of this year.
However, as anyone who has walked past the construction site recently could see, the project is still ongoing and the actual wall hasn’t even been built yet.
This week, when asked the reason for the delay, a spokesperson for the VA blamed the delay on “unforeseen factors,” specifically a less than cooperative construction site.
Work on the part of the wall along Asser Levy Park is now expected to be finished this summer, according to “tentative projections,” the spokesperson, Claudie Benjamin, said. The walls and work along 23rd and 25th street is now expected to continue until the end of the calendar year. Benjamin added that once the work along Asser Levy Place is finished, the park, which is now partially blocked off, should be “like new” at some point in the summer.
As for the difficult work conditions, Benjamin said this was discovered during the excavation for the flood wall’s foundation.
“We found some unanticipated site conditions that required us to bring in archeological and architectural teams to review and opine that we were doing everything safe for the site and the local community and that we didn’t have any archeological sites of significance,” she said.